Image: Checking the wing
NASA
Inside NASA's Orbiter Processing Facility, Discovery astronauts Stephanie Wilson and Lisa Nowak look closely underneath the wing of the shuttle. The crew visited Kennedy Space Center this month to get hands-on experience with the equipment they will use in orbit.
By NBC News space analyst
Special to MSNBC
updated 2/24/2006 5:57:39 PM ET 2006-02-24T22:57:39

For now, NASA's top shuttle managers are holding firm to a schedule that would launch the shuttle Discovery on its second "return to flight" test mission as early as May 10. However, several senior NASA officials have told NBC News privately that launching in May was at best an iffy proposition.

"We haven't given up on May yet," one official said in an e-mail. However, another source advised against making nonrefundable reservations to see the launch. A third official said there was so much to get done and so little "margin" in the schedule that May was looking more and more unlikely. The sources discussed the situation on condition of anonymity because they were not authorized to speak with the press.

The official view is that NASA is targeting May, rather than shifting to the next launch opportunity in July. During a teleconference on Thursday, NASA officials set May 10 as the earliest date for liftoff, with the launch window extending until May 23. "We are under no thought of delaying launch," shuttle program manager Wayne Hale said, according to accounts from participants.

Fuel tank being shipped
To support a May date for Discovery's launch to the international space station, the shuttle's external fuel tank is being shipped this weekend from the hurricane-battered Michoud Assembly Facility, near New Orleans, to Kennedy Space Center in Florida.

The fuel tank has been a key cause for concern — first of all, because it was foam insulation debris from the tank that dealt a mortal blow to the shuttle Columbia in 2003, leading to the craft's destruction, the loss of the crew and a two-year suspension in shuttle flights. The tanks were redesigned, but debris was seen coming off the tank yet again just after Discovery's launch last July. Fortunately, no serious harm was done.

To resolve the continuing problem, engineers at Michoud removed an aerodynamic protective cover where most of the shedding occurred. The key safety concern, according to numerous space workers who have spoken with MSNBC.com in recent days, is that engineers are far from finishing the analysis and wind tunnel testing to verify that the new configuration is safe to fly.

A widespread fear is that the march toward a defined launch date will put undue pressure on the testing team to come up with the "right" answer and meet the schedule. The "wrong" answer — that the modifications to the external covering of the tank are not provably safe — could require returning the tank to Michoud for rebuilding.

"We would then be screwed out of July, too," one official told MSNBC.com in an e-mail.

Even though Hale said there was "no thought" of delay, he has acknowledged in the past that test results might still rule out a May launch. During an "all-hands" meeting earlier this month, Hale told space workers that he hoped the preliminary analysis would be available in March, but that the definitive tests might take until June. And he promised not to push for May if there were any suspicions that the tank modifications were not safe.

“We are going to have a very interesting review on the external tank,” Hale was quoted as saying during Thursday's teleconference.

Restrictive launch windows
For at least this next mission, NASA planners will stick to the hyper-restrictive launch windows that provide adequate lighting for observing any debris falling from the tank. Combined with other standard constraints, this creates launch windows in May, then from July 1 to 19, then from Aug. 29 to Sept. 14, then two short windows at the end of October and the end of December.

Space officials hope that good results on the next flight will lead to the dropping of these lighting requirements, and the consequent widening of launch windows later in the year. However, even if Discovery launches on time and the requirement for a daytime launch is dropped, there are other potential constraints on future flights — including the schedules for fuel tank delivery, as well as for returning the shuttle Endeavour to flight status after a major overhaul.

For example, the earliest launch date for the mission after Discovery's, involving the shuttle Atlantis, was recently slipped from July 1 to August 28 due to a delay in producing another external fuel tank.

Discovery's domino effect
The Atlantis delay has implications for Discovery as well: Like last year’s mission, the upcoming mission must provide a "safe haven" option for the crew, in case astronauts spot potentially fatal damage to the shuttle's heat shield during on-orbit inspections. That option calls for the shuttle crew to take shelter aboard the international space station and wait for another shuttle to pick them up.

The current "safe haven" plan calls for Atlantis to be launched on a rescue mission as early as Aug. 4. That implies that the shuttle's seven crew members would have to hunker down with the station's two long-term residents for almost three months. NASA says that option is workable because the station has more stocks of food and water, and more reliable life support hardware, than it did last year.

The shuttle fleet's third surviving vehicle, Endeavour, had been due to follow Atlantis on the flight rotation in December. However, that mission has now been switched to Discovery. Whether there will be a flight-ready tank on hand by the end of the year remains in doubt.

The bottom line is that the benefits of flying the next mission in May are evaporating, and the slips in the follow-on flight schedule are putting greater strains on the contingency planning for the May launch. Because of this domino effect, a delay of two months makes sense, some space workers have told MSNBC.com.

Issues mount up
The concerns over verifying the safety of the tank modifications are far from the only issues being juggled by the NASA shuttle team. It's normal to encounter such issues during launch preparations, and they are often resolved by assigning extra resources, but this time some officials fear there may be just too many of them to resolve in time for a May liftoff.

Mechanical checks have revealed potential problems with the overhead windows in the crew cabin; with pressure seals and possible contamination in the main engines; and with a leaky hydraulic power unit that was thought to have been fixed. Tile replacement, and in particular the installation of "gap fillers," has lagged behind planned schedules.

Echoes of past problems are also being heard. Some engineers interpret sketchy data from last year's launch as suggesting there really was a debris impact on Discovery's left-wing leading edge, the same location where Columbia suffered its mortal wound in January 2003. In addition, one of the low-level sensors in the fuel tank is showing similar symptoms to an equivalent sensor in Discovery’s flight last year, a problem that led to a significant last-minute delay.

Currently, Discovery's preparations are at condition "yellow," meaning that significant effort will be required to meet the schedule. Officials are hoping to roll Discovery from the Orbiter Processing Facility to the Vehicle Assembly Building on April 6, so that it can be mated to the tank and solid-rocket boosters and rolled out to the pad about April 13.

Dates drive discussions
John Muratore, NASA’s manager for shuttle systems and integration, reportedly concluded Thursday's meeting by acknowledging that a “tremendous amount of engineering work” was being laid out. He wanted everyone to understand that the launch date will be driven by the completion of this required engineering work, and that setting a date was intended to provide a target for concerns to be aimed at.

“We should not be thinking that if we put a launch date out, that means that we will compromise the engineering work to make that launch date,” he insisted, according to another attendee. The purpose, rather, is “to force a discussion about what work there is, that needs to be done – and drive those issues out of the woodwork.”

So far that process has been working, and engineers have clearly been vigorously bringing their concerns forward. If, as a result, there turns out to be too much work to get done before May — and that prospect is widely accepted as likely— then the mission will wait for a July flight with all the safety concerns properly addressed.

Worse things could happen. In the past, when the rough-and-tumble exchanges that now characterize NASA’s meetings was suppressed, worse things did happen. So none of these issues, and no amount of time needed to get it right, should be considered bad news.